Austral was engaged as a specialist marine subcontractor by Ertech to upgrade the Exmouth Boat Harbour’s Service Wharf, Heavy Lift Wharf & Trawler Pen Mooring Facility.
Piles were installed from Austral’s jack-up barge using our Bauer RG16 and ‘rotopile’ piling technique, which was ideally suited to the limestone and mudstone geotechnical profile.
Installation of 101no. 610mm & 406mm diameter piles up to 16m in length
Supply & installation of corrosion protection system to all piles
Vibratory extraction of 45no. redundant steel tubular piles